UFC APEX FIRES
1,289Governing occupant load
3Approved bleacher configurations
2,563Exit capacity provided
1Permit covering the full calendar
Construction · Overview

Where the project stands

Work is in place ahead of the permit record. The corrective path is running in parallel with the September event calendar; nothing on this page assumes the calendar moves.

Phase 3
Current phase
4
Open submittals
2
Trades awaiting as-builts
Sep 29
Target close-out
Master Egress Plan — Phase 3Approved
Fire alarm amendment — under-mezzanine devicesRejected
Fire alarm amendment — resubmittalIn review
Sprinkler as-built — under-bleacher coverageIn review
Places of Assembly occupancy planApproved

Phase indicator

Phase 3 — corrective permit process. Work is in place ahead of the permit record. The corrective path is running in parallel with the September event calendar; nothing on this page assumes the calendar moves.

Timeline

  1. Phase 3 scope lockApril 2026
  2. Egress and occupancy approvalsMay 2026
  3. Alarm amendment clearedAugust 2026
  4. Pre-test / readiness runsSeptember 2026
  5. Final inspectionsBefore September 29

Full milestone tracker →

Contingency
Fallback options are documented for every gate that could slip. Review the contingency plan.