Construction · 05
Pre-Test / Readiness Check
Fire alarm
- Full device matrix walked against approved plan
- Voice intelligibility spot readings at mezzanine and floor
- Battery calc and current draw verified against panel
- Monitoring account confirmed active with central station
Sprinkler
- Hydro certificates in hand for every new branch
- Under-bleacher heads clear of telescopic travel at full deploy
- FDC signage, caps, and access verified
- As-built red-lines reconciled to field
Egress & assembly
- All nine exits swing free and unobstructed
- Cross aisle at foot of every deployed bank measured
- West aisle held at 60 in. clear full length
- Approved plan set physically on site
Rule
A trade does not get scheduled for a final until its readiness sheet is walked and signed by FMC. A failed final costs more calendar than a dry run ever will.