UFC APEX FIRES
1,289Governing occupant load
3Approved bleacher configurations
2,563Exit capacity provided
1Permit covering the full calendar
Construction · 05

Pre-Test / Readiness Check

Dry run per trade before the real final. The point is to catch the snafu before the AHJ is standing on the floor.

Fire alarm

  • Full device matrix walked against approved plan
  • Voice intelligibility spot readings at mezzanine and floor
  • Battery calc and current draw verified against panel
  • Monitoring account confirmed active with central station

Sprinkler

  • Hydro certificates in hand for every new branch
  • Under-bleacher heads clear of telescopic travel at full deploy
  • FDC signage, caps, and access verified
  • As-built red-lines reconciled to field

Egress & assembly

  • All nine exits swing free and unobstructed
  • Cross aisle at foot of every deployed bank measured
  • West aisle held at 60 in. clear full length
  • Approved plan set physically on site
Rule
A trade does not get scheduled for a final until its readiness sheet is walked and signed by FMC. A failed final costs more calendar than a dry run ever will.