Historical Record · 01

Building Timeline

The full history of the building, pre-FMC and FMC era. This is the module that survives staff turnover.

  1. 1998 · Pre-FMC
    Built as light manufacturing

    Original tilt-up shell permitted as F-1 occupancy with no assembly use contemplated.

  2. 2010 · Pre-FMC
    Warehouse and distribution conversion

    Interior racking permit; sprinkler density revised for storage commodity class.

  3. 2019 · Pre-FMC
    UFC acquisition and Phase 1 buildout

    Assembly conversion begins. Master egress approach established for the arena envelope.

  4. 2022 · Pre-FMC
    Phase 2 — plan of record stamped

    Sheet LS-2.2 stamped by James P. Begley, Nevada PE 16000, June 21, 2022.

  5. 2025 · FMC era
    FMC engaged — annual POA strategy

    Single approved envelope replaces per-event submittals for the arena calendar.

  6. 2026 · FMC era
    Phase 3 corrective permit process

    Alarm and sprinkler scope brought onto the permit record ahead of the September run.