Construction · 07
Contingency Plan
If
Fire alarm final does not clear before the September run
Then
Interim notification procedure with staffed fire watch positions at mezzanine and both east horizontal exits; documented to the Bureau in advance of doors.
If
Sprinkler as-builts outstanding at final
Then
Field-verified red-line set accepted at inspection with certified as-built filed within ten days; hydro certificates carried on site.
If
Inspection resource unavailable on an event date
Then
Engine company standby requested; configuration held to Configuration 2 with reduced bleacher deployment until inspection occurs.
If
Occupant load challenged on site
Then
Approved envelope sheet and manifest set produced from the on-site plan package; floor seating reduced to the verified count rather than delaying doors.
Posture
Contingencies are filed with the Bureau in advance where they affect occupancy. Nothing here is a workaround — each option is an interim operational control the department can see and adjust.