Construction · 06
Timeline
- Phase 3 scope lock
Scope frozen with GC and facility ops; corrective path defined.
- Egress and occupancy approvals
Master Egress Plan and Places of Assembly occupancy plan approved.
- Alarm amendment cleared
Resubmittal in review. Governs the fire final.
- Pre-test / readiness runs
Dry run per trade before the AHJ is standing on the floor.
- Final inspections
Target: close out before the September event run closes.