UFC APEX FIRES
1,289Governing occupant load
3Approved bleacher configurations
2,563Exit capacity provided
1Permit covering the full calendar
Construction · 06

Timeline

A living milestone tracker. It starts as a guesstimate and firms up as scope locks — dates move here first, not in someone's inbox.

  1. April 2026
    Phase 3 scope lock

    Scope frozen with GC and facility ops; corrective path defined.

  2. May 2026
    Egress and occupancy approvals

    Master Egress Plan and Places of Assembly occupancy plan approved.

  3. August 2026
    Alarm amendment cleared

    Resubmittal in review. Governs the fire final.

  4. September 2026
    Pre-test / readiness runs

    Dry run per trade before the AHJ is standing on the floor.

  5. Before September 29
    Final inspections

    Target: close out before the September event run closes.